Add a Level of Effort activity to the project.
In the Activity Table, select a WBS element, BLDG - Adding Activities.
On the Edit toolbar, click the Add icon.
In the Activity ID column, type <BA-ADMIN>.
In the Activity Name column, type <Project Administration>.
In the Activity Type list, select Level of Effort.
The exercise is completed.
In the Activity ID column, type <BA-ADMIN>.
In the Activity Name column, type <Project Administration>.