Scope Management
The integration between P6 and Prime allows you to manage the costs and schedules of scope items at the activity level.
Scope items are materials used in an activity. In Prime, scope items are assigned to work packages. Work packages are sent to P6 as leaf-level WBS nodes.
In P6, add activities to work packages to provide a greater level of detail to the project. A work package is a bucket of short-term work used to manage installation of related scope items. Activity data created in P6 can be sent back to Prime to update work package dates and costs.
Projects integrated between P6 and Prime are indicated in a new column, Integrated Project, on the EPS page in P6. WBS nodes that were created from work packages in Prime are indicated by an icon on the Activities page in. The WBS structure for integrated projects is locked in P6. If the work package structure in Prime changes, update the P6 project with the new structure by using the Update from Primavera Prime function.

To access this feature:
On the Actions menu on the Activities page, click Exchange Data, Send to Primavera Prime or Update from Primavera Prime.